Project
Description

Get information about
Colorado’s Power
Pathway in eastern
Colorado

Home > Project Description

Colorado’s Power Pathway

Colorado’s Power Pathway is a $1.7 to $2 billion investment proposed by Xcel Energy to improve the state’s electric grid and enable future renewable energy interconnections around the state. Colorado’s Power Pathway will increase electric reliability, boost the regional economy and create jobs during construction.

While routes for the transmission lines have yet to be determined, we estimate the system will span more than a dozen counties, primarily in eastern Colorado, and include:

  • Approximately 560 to 650 miles of new double-circuit transmission line
  • Four new and four expanded substations
  • First segments in-service by 2025, with other segments complete in 2026 and 2027
  • Endpoints: Fort St. Vrain Substation, Canal Crossing Substation
  • Counties in Study Area: Morgan, Weld
  • Schedule
    • Current Activities: Routing and Siting Studies
    • Permitting: 2022-2023
    • Construction: 2024-2026
    • In-service: 2026

Segment 1
Fort St. Vrain – Canal Crossing

  • Endpoints: Canal Crossing Substation, Goose Creek Substation
  • Counties in Study Area: Cheyenne, Kit Carson, Morgan, Washington, Yuma
  • Schedule
    • Current Activities: Routing and Siting Studies
    • Permitting: 2022-2023
    • Construction: 2023-2025
    • In-service: 2025

Segment 2
Canal Crossing – Goose Creek

  • Endpoints: Goose Creek Substation, May Valley Substation
  • Counties in Study Area: Cheyenne, Kiowa, Prowers, Kit Carson
  • Schedule
    • Current Activities: Routing and Siting Studies
    • Permitting: 2022-2023
    • Construction: 2023-2025
    • In-service: 2025

Segment 3
Goose Creek – May Valley

  • Endpoints: May Valley Substation, Tundra Substation
  • Counties in Study Area: Crowley, Kiowa, Prowers, Pueblo, El Paso, Lincoln
  • Schedule
    • Current Activities: Routing and Siting Studies
    • Permitting: 2022-2023
    • Construction: 2025-2027
    • In-service: 2027

Segment 4
May Valley – Tundra

  • Endpoints: Tundra Substation, Harvest Mile Substation
  • Counties in Study Area: Arapahoe, El Paso, Elbert, Pueblo, Douglas
  • Schedule
    • Current Activities: Routing and Siting Studies
    • Permitting: 2022-2023
    • Construction: 2025-2027
    • In-service: 2027

Segment 5
Tundra – Harvest Mile

  • Endpoints: May Valley Substation, Longhorn Substation
  • Counties in Study Area: Baca, Prowers, Kiowa
  • Schedule
    • Current Activities: Routing and Siting Studies
    • Permitting: 2022-2023
    • Construction: 2023-2025
    • In-service: 2025

Extension
May Valley – Longhorn

  • Endpoints: Fort St. Vrain Substation, Canal Crossing Substation
  • Counties in Study Area: Morgan, Weld
  • Schedule
    • Current Activities: Routing and Siting Studies
    • Permitting: 2022-2023
    • Construction: 2024-2026
    • In-service: 2026

Segment 1
Fort St. Vrain – Canal Crossing

  • Endpoints: Canal Crossing Substation, Goose Creek Substation
  • Counties in Study Area: Cheyenne, Kit Carson, Morgan, Washington, Yuma
  • Schedule
    • Current Activities: Routing and Siting Studies
    • Permitting: 2022-2023
    • Construction: 2023-2025
    • In-service: 2025

Segment 2
Canal Crossing – Goose Creek

  • Endpoints: Goose Creek Substation, May Valley Substation
  • Counties in Study Area: Cheyenne, Kiowa, Prowers, Kit Carson
  • Schedule
    • Current Activities: Routing and Siting Studies
    • Permitting: 2022-2023
    • Construction: 2023-2025
    • In-service: 2025

Segment 3
Goose Creek – May Valley

  • Endpoints: May Valley Substation, Tundra Substation
  • Counties in Study Area: Crowley, Kiowa, Prowers, Pueblo, El Paso, Lincoln
  • Schedule
    • Current Activities: Routing and Siting Studies
    • Permitting: 2022-2023
    • Construction: 2025-2027
    • In-service: 2027

Segment 4
May Valley – Tundra

  • Endpoints: Tundra Substation, Harvest Mile Substation
  • Counties in Study Area: Arapahoe, El Paso, Elbert, Pueblo, Douglas
  • Schedule
    • Current Activities: Routing and Siting Studies
    • Permitting: 2022-2023
    • Construction: 2025-2027
    • In-service: 2027

Segment 5
Tundra – Harvest Mile

  • Endpoints: May Valley Substation, Longhorn Substation
  • Counties in Study Area: Baca, Prowers, Kiowa
  • Schedule
    • Current Activities: Routing and Siting Studies
    • Permitting: 2022-2023
    • Construction: 2023-2025
    • In-service: 2025

Extension
May Valley – Longhorn

Meeting the Need

Transmission is the backbone of the electricity network, with lines and poles moving large amounts of high-voltage power across long distances. Colorado has an open transmission system so power lines carry not only electricity generated by Xcel Energy but by utilities and cooperatives around the state too, benefitting everyone who uses electricity. Transmission planning is also coordinated on a statewide level to ensure projects meet customer needs on a cost-effective and reliable basis.

The Eastern Plains of Colorado is one of the nation’s best areas for wind and solar. New transmission lines encourage construction of wind and solar power plants to bring more low-cost electricity to help meet the needs of our growing state. With these new projects come jobs, lease revenue and increased taxes for rural communities.

For example, in 2020 we completed the Cheyenne Ridge Wind Project in Cheyenne and Kit Carson counties. The 500-megawatts generated and carried by 70 miles of transmission line are enough to power 270,000 average Colorado homes. Over its lifetime, Cheyenne Ridge will produce an estimated $107 million in landowner payments and $29 million in new tax revenue for surrounding communities and counties. More than 200 workers built the project and 24 full-time operations and maintenance jobs were created.

Colorado’s Power Pathway will carry the approximately 5,500 megawatts of new wind, solar and other resources Xcel Energy plans to add through 2030 to meet the state’s growing electricity needs reliably and affordably. The project’s proposed 345-kilovolt transmission system will connect eastern Colorado to the Front Range.

Regulatory & Permitting

The project requires approval from the Colorado Public Utilities Commission (CPUC) for a Certificate of Public Convenience and Necessity (CPCN). In March 2021, we took the first step in the approval process by filing an application with CPUC. Xcel Energy’s application with the CPUC can be found by visiting the Public Utilities Commission website, navigating to E-Filings and entering Proceeding No. 21A-0096E in the Search field. Visit the CPUC website to view regulatory documents associated with the project, including notices, filings, public comments and more. Filing materials can also be found on Colorado’s Power Pathway Regulatory Filings webpage.

Local land use permits may also be required for approval in the counties or municipalities where the project is located.

Schedule of Activities